Since the rooms were not marked in the architectural model, before MEP systems designing, we will indicate the location of bathrooms on the second floor.
Move to the 02-Floor.
|
Room number. |
2.11 |
Room name. |
Bathroom |
|
Room height. |
3000 |
Let's move to pipe systems design. In the beginning, we will place plumbing fixture equipment (toilet, washbasin, shower tray) and design a riser pipe. The riser pipe is supposed to get through all the floors.
Move to the 02-Floor. Let's start building with bathroom 2.41. Here, we will place route points the riser pipe is supposed to be getting through.
|
Route point name. |
SS-1 |
Level |
02-Floor |
|
Vertical offset. |
0 |
Level |
01-Floor |
|
Vertical offset. |
-500 |
Level |
Attic Floor |
|
Vertical offset. |
500 |
Let's move to plumbing fixture arrangement of domestic sewage system.
Use the existing plumbing fixture style to create the toilet:
Plumbing fixture position relative to axis. |
Bottom-Center |
|
Plumbing fixture style. |
Two-piece toilet |
|
Level |
02-Floor |
Let's create new Plumbing fixture styles to place a Shower tray.
General |
||
Material |
none |
|
Overall dimensions |
||
Shower tray type |
Rectangular |
|
Shower tray width |
700 |
|
Shower tray depth |
1100 |
|
Shower tray height |
Pipe material Polypropylene random copolymer |
|
Shower tray legs height |
250 |
|
Domestic sewage |
||
Connection type |
Spigot and Socket |
|
Nominal diameter |
50 |
General |
||
Material |
none |
|
Overall dimensions |
||
Shower tray type |
Rectangular |
|
Shower tray width |
1100 |
|
Shower tray depth |
700 |
|
Shower tray height |
Pipe material Polypropylene random copolymer |
|
Shower tray legs height |
250 |
|
Domestic sewage |
||
Connection type |
Spigot and Socket |
|
Nominal diameter |
50 |
Plumbing fixture position relative to axis. |
Bottom-Right |
|
Plumbing fixture style. |
Shower tray (right hand) |
|
Level |
02-Floor |
To create a washbasin with cabinet, let's copy an object from another project.
Precession. |
90 |
Let's fix the position of the bathroom door:
At this step, we will define relationship between plumbing fixture equipment, will lay pipes and place required elbows and tees.
The plumbing fixture connection process is taken in the priority order, the master plumbing fixture equipment should be connected first.
Main line |
||
Main line Route height |
100 |
|
Offset |
100 |
|
Pipe material |
Polypropylene |
|
Connection type |
Spigot and Socket |
|
Branch line |
||
Main line Route height |
70 |
|
Offset |
100 |
|
Pipe material |
Polypropylene |
|
Connection type |
Spigot and Socket |
Main line |
||
Main line Route height |
100 |
|
Offset |
100 |
|
Pipe material |
Polypropylene |
|
Connection type |
Spigot and Socket |
|
Branch line |
||
Main line Route height |
70 |
|
Offset |
100 |
|
Pipe material |
Polypropylene |
|
Connection type |
Spigot and Socket |
The pipe is in finished state now, all that's left is to place pipe fittings.
Shower tray should be connected to the pipe, leading from the washbasin.
Main line |
||
Main line Route height |
100 |
|
Offset |
100 |
|
Pipe material |
Polypropylene |
|
Connection type |
Spigot and Socket |
|
Branch line |
||
Main line Route height |
100 |
|
Offset |
500 |
|
Pipe material |
Polypropylene |
|
Connection type |
Spigot and Socket |
Let's edit the route, because it was not built correctly.
The placement of the sewer pipes in the bathroom 2.41 is completed.